marco.detering

Project 02 · Operations

Wind Energy Logistics

RoleManaging Director CompaniesZureck · ARBOR Logistics WhereStockholm, Sweden Span2020 — 2024

Before AI, I moved turbines. As Managing Director — first of Zureck Logistic Sweden, then ARBOR Logistics Sweden — I built the foundation for growth and grew the customer base for onshore wind-farm logistics across the Nordics and central Europe.

It's logistics at the heavy end: route surveys, oversized component transport, and the partnerships to pull it off. The work supported delivery of 100+ turbines to wind farms in Sweden, Britain and Ireland, and contributed to the largest onshore wind project of 2022 — 60 turbines. One project even ran outside wind entirely: route survey and initial component transport for a rocket test centre in Kiruna.

This is where the operator's instinct comes from — owning a P&L, building a young company, and getting physical things to remote places on time.

01

100+ turbines delivered

To wind farms across Sweden, Britain and Ireland.

02

Largest 2022 onshore project

Contributed expertise and staff to complete a 60-turbine delivery.

03

Nordics growth

Grew revenue, customer base and partnerships from the ground up as MD.

04

Kiruna rocket centre

Route survey and component transport beyond wind — for a rocket test centre.

What it took

P&L ownershipOperationsPartnerships Route planningTeam buildingHeavy logistics